
Monday, June 16, 2008
more rain

Wednesday, June 11, 2008
Bricks

The courtyard is also poured and bricked (above), complete with fish pond (apparently!)
Sunday, June 08, 2008
flooring and roofing


This picture shows insulation which means roof is on the backpart of the house now.
Friday, June 06, 2008
Washout

However, the gyprocker was able to get the stud walls underway and the window guy came and measured up for the downstairs windows. He gave us some advice about having a serving hatch through the kitchen window to the back. The advice was 'don't do it'. Because there is no planned (at this stage) roof structure for the back patio, the window will be open to the elements and there would undoubtedly be leakage. Fair enough. So three weeks today he'll be ready to install. But will the walls be built? If the rain keeps up, then no! He'll be back next week, or when we have some flooring to measure upstairs.

We also have both floors laid now (basic boards, not finished ones). which means the structure finally looks like a house! The top picture is the second storey, covered in plastic.
Hoping to get the roof on over this weekend but the weatehr forecast doesn't look good. More rain apparently.
Thursday, May 29, 2008
Steel done

14 tonne in total
26 x columns
46 x beams
6 x rafters
139 x floor joists
52 x roof purlins
Roofer measured yesterday and should have wire, insulation, gutter (etc) including roof cladding and some high level wall cladding complete by Wed next week. The plumber has started today, laying pipework and drains etc. Brickie to start Monday and Wall linings on Tuesday next week.
Sunday, May 25, 2008
Connecting Pieces
Wednesday, May 21, 2008
Steel Arrives


Next step is to lay pipe work ready for flooring to go down and to put on the steel part of the roof.
Tuesday, May 13, 2008
Tidying up

This week, the benefits of the concrete and tidy up of the back yard could be seen. Unfortunately, when they came to fit the holding down bolts in preperation for erecting the steel, they couldn't drill with a normal drill because there is too much reo in the way. Need to get core driller in - another delay plus more money.
Sunday, May 04, 2008
Footings


Footings didnt get poured on weekend cause pump was too small and could not setup on street and boom over house. Re scheduled for lunchtime today.
Fence went in ok on Friday. Looks great. also, waterproofing behind retaining walls has been done ready for filling with soil for plants. This week aiming to level site, take away footing spoil and tidy up for steel erection. Also, drill and epoxy the column holding down bolts.
On the fitout side, been thinking more about colour of the floor to ceiling bookcase in the family room. Will put a laminate finish on it so pretty much skys the limit in terms of colour selection. Originally thought white but thinking may be a bit stark. Maybe browny colour? Thinking bottom section to have cupboards with doors and above incl over doorway to be open book case.
Also, want to change window colour back to white. As well as louvres (etc). Want to go back to our original idea of similar to locaql development. Looked at roof tiles, going to run with a flat profiled, shingle looking concrete tile.
Monday, April 21, 2008
Too much rain

Starting to wonder whether knocking down the remaining back walls was a good idea or not...
Thinking about kitchen splashback window. It was to be long and narrow abouve the benchtop. Want to delete it as it faces west and concerned with sun / heat. We can always get similar affect with colorback glass splashback.
Thursday, April 10, 2008
Underpinning
We had a quote this week to do the underpinning of the back of the house along the side so we can excavate for the garage and laundry. At $16,000 we made the decision to knock down those remaining two outer walls and start again. Much cheaper and won't impact on the timeline.
At the moment waiting for the steel detailing to be finished so steel can be fabricated. Latest estimate is to erect on May 5th.
At the moment waiting for the steel detailing to be finished so steel can be fabricated. Latest estimate is to erect on May 5th.
Sunday, March 30, 2008
Demo finished
Wednesday, March 19, 2008
Demolition
Tuesday, March 04, 2008
Pool poured

According to the Canada Bay online DA tracking tool, it looks like all is complete for senior officer to sign off. Need to call to understand next step & timing. Locked away construction certificate (CC) guy.
Monday, February 25, 2008
Pool begins
Monday, February 18, 2008
Steel
Met engineer this week. Structural steel framing coming together. Next step is meeting steel detailer to walk him through and get him to produce workshop drawings for fabricator. Sounds like such a long winded process but the way it is designed, the steel bones should go up in 4-5 days. From then, brickie, structural carpenter, roofer, windows and then lock up. Hoping lock up will be early May.
Steel framing plan came back from engineer. Will need to put another column at back of house. If not the beam is way to deep 360mm. Will not get that sexy exposed steel look trying to achieve. Ok, means need to rethink glazing. Bifolds that stack into column, sliders etc. Sort of leaning towards sliders for practicality with kids and user friendly. Only double sliders.
Steel framing plan came back from engineer. Will need to put another column at back of house. If not the beam is way to deep 360mm. Will not get that sexy exposed steel look trying to achieve. Ok, means need to rethink glazing. Bifolds that stack into column, sliders etc. Sort of leaning towards sliders for practicality with kids and user friendly. Only double sliders.
Tuesday, February 12, 2008
Baths and water


Also discussed carpets for upstairs and whether or not to carpet the staircase or leave wooden. I think carpet.
Still waiting for stormwater drawings to submit to council.
Trying to get to window contractor this week to discuss and negotiate. Even though most windows need be site measured hoping he can order framing material, powdercoat etc so when ready he can hit it.
Monday, February 04, 2008
More rain
Big push between now and Easter to get design sorted, materials ordered and steel erected. Weathered has put us further back this week. Forecast is for rain all week. The back yard is like a bad day in Beirut. Dirt has washed down driveway and onto street. Waiting for it to stop so it can be shoveled out.
Demo bloke came out last nite. Will lock him in for end of month. Need more talks with the architect. Need details drawn and more dimensions for window and steel guy.
Demo bloke came out last nite. Will lock him in for end of month. Need more talks with the architect. Need details drawn and more dimensions for window and steel guy.
Thursday, January 24, 2008
retaining wall

Unfortunately a part of the neighbours fence has fallen down because of the earthworks and the rain so we will have to erect a temporary fix.
Tuesday, January 22, 2008
Heavy Rain
Council has approved one of the two alternatives we put forward after their initial rejection, so now we are having the drawings altered and hoping to resubmit this Friday.
Subscribe to:
Posts (Atom)