Not nearly finished but nearly ready to move in (one more week...but heard that before!) This week the carpenter came on Thursday but when he arrived to install the front door he found they had delivered the wrong size door jambs. He made do with what he had, just joined them - won't notice once painted. Then today we had to wait till almost midday before the other doors were delivered. The skirting and architraves around all the doors are almost complete now.
The kids toilet was also installed (and tiles patched) so that was a major achievement this week. And the downlights were fitted as well as the alarm system. We also got the hot water system installed along with some strange control pads which aparently have to go on the wall of each area requiring instantaneous hot water.